Dargues Gold Project Stage 1 & 2 - Tailings Dam Facility
Client Information
Client: |
Diversified Minerals / Big Island Mining
|
Services: |
Civil |
Duration: |
March 2020 - Current |
Value: |
$10M |
Summary
Scope of Works:
- Raise existing embankment 3.1m and extend the upstream HDPE lining, involving approx. 480,000m3 of earthworks, including cut to fill and load and haul from existing facility stockpiles
- Excavating and shaping the embankment to accommodate the installation of the HDPE basin lining
- Supply and install of 110,000m2 HDPE lining for the basin and embankment, with the embankment lining to be extended to the final overall height of RL 712.00m
- Extension of the LCRS and Underground Drainage pipework
- 75,000m3 crushing and screening of Various Classified Materials