Dargues Gold Project Stage 1 & 2 - Tailings Dam Facility

Client Information

Client: Diversified Minerals / Big Island Mining
Services:
Duration: March 2020 - Current
Value: $10M

Summary

Scope of Works:

  • Raise existing embankment 3.1m and extend the upstream HDPE lining, involving approx. 480,000m3 of earthworks, including cut to fill and load and haul from existing facility stockpiles
  • Excavating and shaping the embankment to accommodate the installation of the HDPE basin lining
  • Supply and install of 110,000m2 HDPE lining for the basin and embankment, with the embankment lining to be extended to the final overall height of RL 712.00m
  • Extension of the LCRS and Underground Drainage pipework
  • 75,000m3 crushing and screening of Various Classified Materials