VMS

VMS allows us to provide our global customers base with high quality and price competitive equipment and machinery, engineer and manufactured to meet the needs of the industries we service.

Projects

Tomingley Gold Mine

Client Information

Client: Tomingley Gold Mine Operations Pty Ltd (Alkane Resources)
Services:
Duration: 2011 - 2013
Value: $19M
Location: Tomingley, NSW

Summary

Construction of New Gold Mine & Overburden Strip

Scope of Works:

Construction of new gold mine and overburden strip, as follows:

  • 750,000m3 of Bulk and Detailed Earthworks
  • Construction of hardstand, plant area and laydown facilities
  • Access roads
  • Site drainage including culverts
  • Pavements
  • Bunds and earthern berms to redirect storm water
  • Construction of a new Tailings Dam Facility
  • Construction of raw water ponds for reticulation of the system
  • Overburden strip of the 3 main pits onsite
  • Construction of ROM Pad
  • All preliminary Site Earthworks. Construction of Tailings Dam including Dam Lining